AwardTape / Contracts / FA4877-25-F-0251
FA4877-25-F-0251: $517K Department of the Air Force Award to Olgoonik General, LLC
This project will consist of the field investigation, design, plans, specifications, installation, and testing in connection with the replace fire alarm panels project in bldg 12 at davis-monthan afb, arizona.. Contracting activity: FA4877 355 CONS PK. Estimated completion: 2027-01-16.
$517K contract action / $517K cumulative ceiling / COMPETITION NOT STATED / 2027-01-16 completion / FA4877 FA4877 355 CONS PK
1. Contract Summary & Primary Sources
| Contract Number (PIID) | FA4877-25-F-0251 (unhyphenated: FA487725F0251) · Parent Vehicle: FA4877-24-D-0013 |
|---|---|
| Prime Contractor (Awardee) |
Olgoonik General, LLC
(Arizona)
FY2024-FY2026 Federal Defense Portfolio: $30.0M obligated across 42 contracts
|
| Obligated Amount | $517,295 |
| Cumulative Face Value / Ceiling | USAspending Base IDV Ceiling: $517,295 |
| USAspending / FPDS Obligation History | Base Record Obligated: $517,295 (signed 2025-07-31, latest FPDS action 2025-07-31) · 8 Issued Delivery/Task Order(s) totaling $9,564,570 |
| Awarding Branch / Agency | Department of the Air Force |
| Contracting Command & DoDAAC | FA4877: FA4877 355 CONS PK |
| Competition & Contract Structure | COMPETITION NOT STATED · Delivery Order / Firm-Fixed-Price (FFP) |
| Product / Service & Industry Codes | PSC Z2JZ (Repair Or Alteration Of Miscellaneous Buildings) · NAICS 236220 (Commercial And Institutional Building Construction) |
| Work Locations & Funding | Primary Place of Performance: Arizona |
| Estimated Completion Date | 2027-01-16 |
| Verified Primary Sources |
2. Verbatim Announcement & Scope Breakdown
This project will consist of the field investigation, design, plans, specifications, installation, and testing in connection with the replace fire alarm panels project in bldg 12 at davis-monthan afb, arizona.
3. Subcontractor, Supply Chain & Capture Intelligence
Subcontracting & Material Supply Window
- Prime Awardee: Olgoonik General, LLC
- Delivery Runway: Active through 2027-01-16
- Requirement Scope: This project will consist of the field investigation, design, plans, specifications, installation, and testing in connection with the replace fire alarm panels project in bldg 12 at davis-monthan afb, arizona.
- Federal Supply Class: PSC Z2JZ (Repair Or Alteration Of Miscellaneous Buildings)
- BD Action: Reference Prime Contract FA4877-25-F-0251 when contacting Olgoonik General, LLC Supply Chain / Small Business Liaison Officer.
Buying Command & Recompete Posture
- Buying Command: FA4877 (FA4877 355 CONS PK)
- Acquisition Method: COMPETITION NOT STATED
- FOIA Jurisdiction: Department of the Air Force FOIA (AFLCMC / AFRL / AFSC) (Official Portal)
- Capture Action: Request Section B CLIN ceiling structure and Section C Statement of Work below to benchmark deliverable requirements.
Issued Task & Delivery Orders under FA4877-25-F-0251 (8 shown, $9.6M obligated)
| Order PIID | Obligated | Awardee | Start / Latest Action | End Date | Order Scope |
|---|---|---|---|---|---|
| FA487725F0250 | $4.6M | Olgoonik General, LLC | 2025-07-31 / 2025-07-31 | 2026-06-30 | Renovate b1550 for wbs for 34 wps 88 tes 355 amxs beddown |
| FA487725F0249 | $2.0M | Olgoonik General, LLC | 2025-07-31 / 2025-07-31 | 2026-08-31 | Repair of b1634 492nd sow wrm and 355th mdg |
| FA487725F0152 | $875K | Olgoonik General, LLC | 2025-04-22 / 2026-03-24 | 2026-07-20 | Delivery / task order |
| FA487725F0277 | $773K | Olgoonik General, LLC | 2025-08-21 / 2025-08-21 | 2026-06-23 | Delivery / task order |
| FA487725F0230 | $499K | Olgoonik General, LLC | 2025-07-22 / 2026-03-17 | 2026-05-31 | A. the macc is designed to provide a flexible, competitive, and responsive contractual capability to perform design-build and bid-build construction work at davis-monthan afb, az. and luke afb. |
| FA487726F0135 | $423K | Olgoonik General, LLC | 2026-04-22 / 2026-04-22 | 2027-01-28 | Eol sprinkler replacement bldgs: 4224, 3750, 5029, 304, 4824, and 79 . |
| FA487726F0140 | $421K | Olgoonik General, LLC | 2026-04-28 / 2026-04-28 | 2026-09-27 | To repair/replace multiple fire hydrants at davis monthan afb |
| FA487724F0231 | $250 | Olgoonik General, LLC | 2024-09-10 / 2024-09-10 | 2024-10-01 | Task order to satisfy the minimum dollar amount required for the base multiple award construction contract contract. |
Recent Contract Actions from Buying Office FA4877 (FA4877 355 CONS PK)
| Date | Contract (PIID) | Prime Contractor | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-08-06 | FA4877-26-P-0024 | Dragoon Technology | $9.9M | - | Dragoon Technology wins $9.9M contract for non-recurring engineering activities to integrate energetics into the internally developed. Naval... |
| 2026-03-25 | FA4877-26-D-0007 | Dni Trend Joint Ventures, LLC | $350.0M | Sep 9, 2031 | DNI Trend JV and 2 others share $350.00M contract for a construction program to include maintenance, repair, alterations, mechanical, electr... |
| 2025-12-18 | FA4877-26-F-0161 | Arizona Industries for the Blind | $20.3M | - | Arizona Industries for the Blind wins $20.3M contract for warehouse and storage services. Defense Logistics Agency Distribution small busine... |
Other Recent Department of War Awards to Olgoonik General, LLC
| Date | Contract (PIID) | Branch | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2025-09-08 | W9127S-25-D-A004 | Army | $45.0M | Sep 7, 2030 | Olgoonik General wins $45.0M contract for various minor construction projects. U.S. Army Corps of Engineers work through Sep 7, 2030. |
4. Underlying Contract Files (Section B Pricing & Section C Statement of Work)
Pre-Filled FOIA Request Letter for FA4877-25-F-0251
Routed to Department of the Air Force FOIA (AFLCMC / AFRL / AFSC) · Official Agency FOIA Portal ↗