W9127S-23-F-6055: $263K Department of the Army Award to Structsure Projects Inc
Design build initial outfitting project for emergency power plant replacement for joint base lewis-mcchord, madigan ARMY medical center, wa.. Contracting activity: W076 ENDIST LITTLE ROCK. Estimated completion: 2028-06-28.
$263K contract action / $59.3M cumulative ceiling / COMPETITION NOT STATED / 2028-06-28 completion / W9127S W076 ENDIST LITTLE ROCK
1. Contract Summary & Primary Sources
| Contract Number (PIID) | W9127S-23-F-6055 (unhyphenated: W9127S23F6055) · Parent Vehicle: W9127S-23-D-6024 |
|---|---|
| Prime Contractor (Awardee) |
Structsure Projects Inc
(Washington)
FY2024-FY2026 Federal Defense Portfolio: $184.4M obligated across 45 contracts
|
| Obligated Amount | $262,749 |
| Cumulative Face Value / Ceiling | USAspending Base IDV Ceiling: $59,284,961 |
| USAspending / FPDS Obligation History | Base Record Obligated: $262,749 (signed 2023-09-22, latest FPDS action 2026-03-19) · 8 Issued Delivery/Task Order(s) totaling $72,896,827 |
| Awarding Branch / Agency | Department of the Army |
| Contracting Command & DoDAAC | W9127S: W076 ENDIST LITTLE ROCK |
| Competition & Contract Structure | COMPETITION NOT STATED · Delivery Order / Firm-Fixed-Price (FFP) |
| Product / Service & Industry Codes | PSC Z2DA (Repair Or Alteration Of Hospitals And Infirmaries) · NAICS 236220 (Commercial And Institutional Building Construction) |
| Work Locations & Funding | Primary Place of Performance: Washington |
| Estimated Completion Date | 2028-06-28 |
| Verified Primary Sources |
2. Verbatim Announcement & Scope Breakdown
USAspending / FPDS Transaction Description (Contract W9127S23F6055)
Design build initial outfitting project for emergency power plant replacement for joint base lewis-mcchord, madigan ARMY medical center, wa.
3. Subcontractor, Supply Chain & Capture Intelligence
For Tier-2 / Tier-3 Subcontractors & Suppliers
Subcontracting & Material Supply Window
- Prime Awardee: Structsure Projects Inc
- Delivery Runway: Active through 2028-06-28
- Requirement Scope: Design build initial outfitting project for emergency power plant replacement for joint base lewis-mcchord, madigan ARMY medical center, wa.
- Federal Supply Class: PSC Z2DA (Repair Or Alteration Of Hospitals And Infirmaries)
- BD Action: Reference Prime Contract W9127S-23-F-6055 when contacting Structsure Projects Inc Supply Chain / Small Business Liaison Officer.
For Competing Primes & Capture Managers
Buying Command & Recompete Posture
- Buying Command: W9127S (W076 ENDIST LITTLE ROCK)
- Acquisition Method: COMPETITION NOT STATED
- FOIA Jurisdiction: Army Contracting Command (ACC) FOIA Officer (usarmy.redstone.acc.mbx.hqaccfoia@army.mil)
- Capture Action: Request Section B CLIN ceiling structure and Section C Statement of Work below to benchmark deliverable requirements.
Issued Task & Delivery Orders under W9127S-23-F-6055 (8 shown, $72.9M obligated)
| Order PIID | Obligated | Awardee | Start / Latest Action | End Date | Order Scope |
|---|---|---|---|---|---|
| W912DY25F2525 | $50.4M | Structsure Projects Inc | 2025-05-14 / 2026-03-04 | 2029-08-26 | Base replace bas & vavs |
| W9127S23F6052 | $12.1M | Structsure Projects Inc | 2023-09-20 / 2026-02-17 | 2029-02-24 | The defense health agency-facilities enterprise requires design, construction, initial outfitting, and transition services for the fy23 ft bragg womack ARMY medical center surgical suite expansion and blood donor center addition-alteration ... |
| W9127825FA312 | $6.9M | Structsure Projects Inc | 2025-09-29 / 2025-09-29 | 2027-11-03 | Replace unit substation/switchgear building 2268, naval hospital pensacola, nas pensacola, florida |
| W9126G23F0298 | $1.5M | Structsure Projects Inc | 2023-11-13 / 2026-04-24 | 2027-04-10 | Dunn dental clinic construction |
| W9127S23F6048 | $1.1M | Structsure Projects Inc | 2023-09-18 / 2026-02-24 | 2027-11-03 | Joint base lewis mcchord, madigan ARMY medical center, building 9040, repair potable water system. |
| W912DY23F0513 | $907K | Structsure Projects Inc | 2023-09-30 / 2025-06-05 | 2027-05-12 | Construction- base |
| W912DY24F0612 | $0 | Structsure Projects Inc | 2024-09-27 / 2025-08-26 | 2025-07-14 | Naval hospital bremerton repairs lr matoc |
| W9127S23F6040 | -$10K | Structsure Projects Inc | 2023-02-10 / 2024-09-10 | 2029-02-08 | Guaranteed minimum |
Tier-2 Subcontract Reporting Status (FAR 52.204-10): Prime contractors report first-tier subcontracts of $30,000 or more to the Federal Subaward Reporting System (FSRS) by the end of the month following subcontract award. Under DFARS 252.219-7003, prime awards exceeding $750,000 ($1.5M for construction) carry mandatory small-business subcontracting plans. Component and subsystem suppliers should contact Structsure Projects Inc Supply Chain / Small Business Liaison referencing contract W9127S-23-F-6055.
Recent Contract Actions from Buying Office W9127S (W076 ENDIST LITTLE ROCK)
| Date | Contract (PIID) | Prime Contractor | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-08-19 | W9127S-22-D-0026 | Great Lakes Dredge & Dock | $12.3M | Aug 20, 2027 | Great Lakes Dredge & Dock gets $12.3M modification for long-term capability, station dredging on the McClellan-Kerr Arkansas River Navigatio... |
| 2026-08-03 | W9127S-26-C-A009 | BL Harbert International | $37.6M | Jan 31, 2029 | BL Harbert International wins $37.6M contract for an F-35 Special Access Program Facility. U.S. Army Corps of Engineers $37.6M obligated now... |
| 2026-04-07 | W9127S-26-C-A006 | BL Harbert International | $40.9M | Mar 23, 2028 | BL Harbert International wins $40.9M contract for construction of an approximately 25,000-square-foot. U.S. Army Corps of Engineers $40.9M o... |
| 2025-12-11 | W9127S-26-C-A001 | BL Harbert International | $61.4M | Mar 21, 2028 | BL Harbert International wins $61.4M contract for F-35 program, supporting multiple countries simultaneously. U.S. Army Corps of Engineers $... |
| 2025-11-13 | W9127S-26-C-A002 | Red Eagle 3 JV of Coweta | $22.9M | Nov 23, 2027 | Red Eagle 3 JV of Coweta wins $22.9M contract for design-build services for the Pine Bluff Arsenal Waterline Replacement. U.S. Army Corps of... |
| 2025-09-08 | W9127S-25-D-A004 | Olgoonik General | $45.0M | Sep 7, 2030 | Olgoonik General wins $45.0M contract for various minor construction projects. U.S. Army Corps of Engineers work through Sep 7, 2030. |
4. Underlying Contract Files (Section B Pricing & Section C Statement of Work)
Document Status: Not yet on file. The government publishes the award notice and obligation record above, but does not post the underlying Section C Statement of Work (SOW), Section B line-item pricing schedule (CLINs), or Sole-Source Justification & Approval (J&A) online.
Free DIY 5 U.S.C. 552 Generator ($0 Cost)
Pre-Filled FOIA Request Letter for W9127S-23-F-6055
Routed to Army Contracting Command (ACC) FOIA Officer (usarmy.redstone.acc.mbx.hqaccfoia@army.mil) · Official Agency FOIA Portal ↗
Optional Anonymous Filing via AwardTape Research: Prefer to keep your company name off the agency's public FOIA log? Enter your work email and AwardTape will track or file this request under AwardTape Research and email you when the agency responds.