W9127S-25-F-0071: $5.6M Department of the Army Award to Koontz Electric Company, Incorporated
Mcc and 480v switchgear replacement at beaver power plant in benton county, arkansas. issued under swpa6 electrical equipment rehabilitation and replacement matoc. work to be complete within 756 days of ntp. dates on car are estimates only.. Contracting activity: W076 ENDIST LITTLE ROCK. Estimated completion: 2027-07-16.
$5.6M contract action / $5.6M cumulative ceiling / COMPETITION NOT STATED / 2027-07-16 completion / W9127S W076 ENDIST LITTLE ROCK
1. Contract Summary & Primary Sources
| Contract Number (PIID) | W9127S-25-F-0071 (unhyphenated: W9127S25F0071) · Parent Vehicle: W9127S-23-D-0002 |
|---|---|
| Prime Contractor (Awardee) |
Koontz Electric Company, Incorporated
(Arkansas)
FY2024-FY2026 Federal Defense Portfolio: $87.0M obligated across 17 contracts
|
| Obligated Amount | $5,631,437 ($5.6M) |
| Cumulative Face Value / Ceiling | USAspending Base IDV Ceiling: $5,631,437 |
| USAspending / FPDS Obligation History | Base Record Obligated: $5,631,437 (signed 2025-05-29, latest FPDS action 2025-07-18) · 1 Issued Delivery/Task Order(s) totaling $95,880 |
| Awarding Branch / Agency | Department of the Army |
| Contracting Command & DoDAAC | W9127S: W076 ENDIST LITTLE ROCK |
| Competition & Contract Structure | COMPETITION NOT STATED · Delivery Order / Firm-Fixed-Price (FFP) |
| Product / Service & Industry Codes | PSC Z2QA (Repair Or Alteration Of Restoration Of Real Property (Public Or Private)) · NAICS 237990 (Other Heavy And Civil Engineering Construction) |
| Work Locations & Funding | Primary Place of Performance: Arkansas |
| Estimated Completion Date | 2027-07-16 |
| Verified Primary Sources |
2. Verbatim Announcement & Scope Breakdown
Mcc and 480v switchgear replacement at beaver power plant in benton county, arkansas. issued under swpa6 electrical equipment rehabilitation and replacement matoc. work to be complete within 756 days of ntp. dates on car are estimates only.
3. Subcontractor, Supply Chain & Capture Intelligence
Subcontracting & Material Supply Window
- Prime Awardee: Koontz Electric Company, Incorporated
- Delivery Runway: Active through 2027-07-16
- Requirement Scope: Mcc and 480v switchgear replacement at beaver power plant in benton county, arkansas. issued under swpa6 electrical equipment rehabilitation and replacement matoc. work to be complete within 756 days of ntp. dates on car are estimates only.
- Federal Supply Class: PSC Z2QA (Repair Or Alteration Of Restoration Of Real Property (Public Or Private))
- BD Action: Reference Prime Contract W9127S-25-F-0071 when contacting Koontz Electric Company, Incorporated Supply Chain / Small Business Liaison Officer.
Buying Command & Recompete Posture
- Buying Command: W9127S (W076 ENDIST LITTLE ROCK)
- Acquisition Method: COMPETITION NOT STATED
- FOIA Jurisdiction: Army Contracting Command (ACC) FOIA Officer (usarmy.redstone.acc.mbx.hqaccfoia@army.mil)
- Capture Action: Request Section B CLIN ceiling structure and Section C Statement of Work below to benchmark deliverable requirements.
Issued Task & Delivery Orders under W9127S-25-F-0071 (1 shown, $96K obligated)
| Order PIID | Obligated | Awardee | Start / Latest Action | End Date | Order Scope |
|---|---|---|---|---|---|
| W9127S23F0001 | $96K | Koontz Electric Company, Incorporated | 2022-10-07 / 2025-03-03 | 2025-04-22 | Greers ferry motor control centers/ac-dc |
Recent Contract Actions from Buying Office W9127S (W076 ENDIST LITTLE ROCK)
| Date | Contract (PIID) | Prime Contractor | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-08-19 | W9127S-22-D-0026 | Great Lakes Dredge & Dock | $12.3M | Aug 20, 2027 | Great Lakes Dredge & Dock gets $12.3M modification for long-term capability, station dredging on the McClellan-Kerr Arkansas River Navigatio... |
| 2026-08-03 | W9127S-26-C-A009 | BL Harbert International | $37.6M | Jan 31, 2029 | BL Harbert International wins $37.6M contract for an F-35 Special Access Program Facility. U.S. Army Corps of Engineers $37.6M obligated now... |
| 2026-04-07 | W9127S-26-C-A006 | BL Harbert International | $40.9M | Mar 23, 2028 | BL Harbert International wins $40.9M contract for construction of an approximately 25,000-square-foot. U.S. Army Corps of Engineers $40.9M o... |
| 2025-12-11 | W9127S-26-C-A001 | BL Harbert International | $61.4M | Mar 21, 2028 | BL Harbert International wins $61.4M contract for F-35 program, supporting multiple countries simultaneously. U.S. Army Corps of Engineers $... |
| 2025-11-13 | W9127S-26-C-A002 | Red Eagle 3 JV of Coweta | $22.9M | Nov 23, 2027 | Red Eagle 3 JV of Coweta wins $22.9M contract for design-build services for the Pine Bluff Arsenal Waterline Replacement. U.S. Army Corps of... |
| 2025-09-08 | W9127S-25-D-A004 | Olgoonik General | $45.0M | Sep 7, 2030 | Olgoonik General wins $45.0M contract for various minor construction projects. U.S. Army Corps of Engineers work through Sep 7, 2030. |
Other Recent Department of War Awards to Koontz Electric Company, Incorporated
| Date | Contract (PIID) | Branch | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-03-12 | W911XK-26-C-A009 | Army | $45.4M | Jan 9, 2029 | Koontz Electric wins $45.4M contract for construction of a new Soo Locks electrical duct bank, including new duct bank, manholes. U.S. Army ... |
| 2026-02-02 | W9128F-26-C-A012 | Army | $14.0M | Jan 30, 2028 | Koontz Electric wins $14.0M contract for a 15kV dam switchgear upgrade. U.S. Army Corps of Engineers $14.0M obligated now signed Feb 2, 2026... |
| 2025-09-23 | W911XK-25-C-A036 | Army | $8.2M | Apr 11, 2028 | Koontz Electric wins $8.2M contract for Soo Locks 15kV switchgear replacement construction project. U.S. Army Corps of Engineers $8.2M oblig... |
4. Underlying Contract Files (Section B Pricing & Section C Statement of Work)
Pre-Filled FOIA Request Letter for W9127S-25-F-0071
Routed to Army Contracting Command (ACC) FOIA Officer (usarmy.redstone.acc.mbx.hqaccfoia@army.mil) · Official Agency FOIA Portal ↗