AwardTape / Budget / Reprogramming / FY 25-03
T-AO Fleet Oiler: $43.0M reprogrammed (FY 25-03)
DoD asked the congressional defense committees to approve $43.0M in this prior-approval reprogramming action (FY2025 serial 25-03), dated Jan 8, 2025. Largest increase: Auxiliaries, craft, and nrior-year nrogram costs +$43.0M (Shipbuilding and Conversion, Navy). Largest source: Modification of aircraft -$6.1M (Aircraft Procurement, Navy).
| Type | Prior approval (DD 1415-1) |
|---|---|
| Serial | FY 25-03 |
| Document date | Jan 8, 2025 from file name |
| Transfer between appropriations | Yes |
| Stated total | $43.0M increases / $43.0M decreases |
| Parse check | Appropriation subtotals match the totals printed on the form; some line items may be missing or misread. Check the source PDF. |
| Source | DD 1415 PDF / 3 pages |
This reprogramming action transfers$43.0 million between Navy appropriations. This reprogramming action uses $43.0 million of general transfer authority pursuant to section 8005 of division A of Public Law 118-47, the Department of Defense Appropriation Act, 2024, and section 1001 of Public Law 118-31, the National Defense Authorization Act for Fiscal Year (FY) 2024.
| Appropriation | Years | Change |
|---|---|---|
| Shipbuilding and Conversion, Navy receives | 24/28 | +$43.0M |
| Aircraft Procurement, Navy gives | 24/26 | -$10.6M |
| Other Procurement, Navy gives | 24/26 | -$8.0M |
| Research, Development, Test and Evaluation, Navy gives | 24/25 | -$24.3M |
| Program | Program base | Change | Revised |
|---|---|---|---|
| Auxiliaries, craft, and nrior-year nrogram costs Shipbuilding and Conversion, Navy 24/28 BA 05: Auxiliaries, craft, and nrior-year nrogram costs Funds are required to fully fund the gross weapon system cost ofT-AO 214 in FY 2024. The recently negotiated eight ship block buy contract resulted in a cost of$858.42 million, resulting in a$43.0 million shortfall. Of the$43.0 million,$36.4 million is required to restore funds t ... | Base $815.4M | +$43.0M | Revised $858.4M |
| TAO Fleet Oiler Shipbuilding and Conversion, Navy 24/28 BA 05: Auxiliaries, craft, and nrior-year nrogram costs | +$32.4M |
| Program | Program base | Change | Revised |
|---|---|---|---|
| Modification of aircraft Aircraft Procurement, Navy 24/26 BA 05: Modification of aircraft This is a congressional special interest item. SAC-D Denied | Base $173.7M | -$6.1M | Revised $167.6M |
| Info Systems Security Program (ISSP) Other Procurement, Navy 24/26 BA 02: Communications & Electronics Eguip Funds are available due to the deferment of procurement of general purpose COMSEC devices as a result of under-execution. This is a congressional special interest item. | Base $153.6M | -$5.0M | Revised $148.6M |
| 0305251N Cyberspace Operations Forces and Force Support Research, Development, Test and Evaluation, Navy 24/25 BA 07: Operational system development Funds are available because all requirements have been satisfied, and these funds are excess to need. There are no kno additional requirements for this funding. | Base $9.0M | -$4.9M | Revised $4.1M |
| MH-60 Series Aircraft Procurement, Navy 24/26 BA 05: Modification of aircraft This is a congressional special interest item. SAC-D Denied E-2 Series | Base $104.2M | -$4.5M | Revised $99.7M |
| 0603178N Large Unmanned Surface Vehicles (LUSV) Research, Development, Test and Evaluation, Navy 24/25 BA 04: Advanced Component Development and Proto!)'pes This is a congressional special interest item. 0603795N Land Attack Technology | Base $102.6M | -$4.3M | Revised $98.3M |
| ████████████ | ████████████ | ████████████ | ████████████ |
| ████████████ | ████████████ | ████████████ | ████████████ |
| ████████████ | ████████████ | ████████████ | ████████████ |
| ████████████ | ████████████ | ████████████ | ████████████ |
Trace Pentagon budget lines (R-1 / P-1) directly to prime contracts, incumbents & expiring awardsMatch every program element to the contracts that fund it, see who holds the work, and get alerted when it recompetes - 7-day free trial. | |||
Tracked vehicles in this lane (Maritime autonomy): Navy USV family of systems MAC / SOCOM maritime fly-away autonomy kit
Budget books show money requested, enacted and spent by fiscal year before contracts show it. Enacted procurement money stays available to obligate for 3 years, RDT&E for 2 years and shipbuilding for 5, so a line funded this year turns into contract awards over the following 1 to 5 years. DoD contract actions then publish on USAspending about 90 days after signing (DFARS PGI 204.6), so the awards database trails these budget lines by months to years. Reprogramming actions move enacted money between accounts during the year, usually ahead of the awards it funds.
Sources
Related
TAO Fleet OilerMH-60 SeriesPollution Control EquipmentInfo Systems Security Program (ISSP)Command Support EquipmentLarge Unmanned Surface Vehicles (LUSV)Small and Medium Unmanned Undersea VehiclesTraining System AircraftManagement HQ - R&DNavy Strategic CommunicationsCyberspace Operations Forces and Force SupportNavy USV family of systems MACSOCOM maritime fly-away autonomy kit
Export CSV spreadsheets, query the API or get the daily contract email.
Pay as you go: $49 one-time for 1,000 API calls and browser CSV downloads (no account needed), or $0.02/call ($0.05 daily list). Subscriptions: Full Tape email $49/mo, Terminal $199/mo (10,000 calls/mo + CSV export), Team $599/mo (5 seats, 50,000 calls/mo).