Shipbuilding special transfer authority: $6.3M reprogrammed (FY 25-05)

DoD reprogrammed $6.3M in this internal reprogramming action (FY2025 serial 25-05), dated Nov 5, 2024. Largest increase: Expeditionary Fast Transport (EPF) +$6.3M (Shipbuilding and Conversion, Navy). Largest source: DDG-51 -$6.3M (Shipbuilding and Conversion, Navy).

TypeInternal (DD 1415-3)
SerialFY 25-05
Document dateNov 5, 2024 from PDF metadata
Transfer between appropriationsNo
Stated total$6.3M increases / $6.3M decreases
Parse checkParsed line items match the totals printed on the form ($6.3M in increases).
SourceDD 1415 PDF / 1 page, 1 read by OCR
Data & CSV export: $49 for 1,000 API calls + CSV download (no account) Full Tape email $49/mo Terminal $199/mo (10,000 calls/mo)
Free sample JSONAll plans
Summary on the form

This reprogramming action transfers funds within the Shipbuilding and Conversion, Navy 14/25 appropriation pursuant to section 8078 of division A of Public Law 118-47, the Department of Defense Appropriations Act, 2024, for ship cost increases. These actions are determined to be necessary in the national interest. This reprogramming action meets all administrative and legal requirements, and none of the items has been previously denied by the Congress.

Accountsfrom and to
AppropriationYearsChange
Shipbuilding and Conversion, Navy
receives
14/25+$6.3M
Shipbuilding and Conversion, Navy
gives
14/25-$6.3M
Increases1 line / +$6.3M
ProgramProgram baseChangeRevised
Expeditionary Fast Transport (EPF)
Shipbuilding and Conversion, Navy 14/25 BA 03: Amphibious ships
Funds are required to liquidate necessary ship cost increases resulting from material inflation and labor rate adjustments on USNS POINT LOMA (EPF 15). This will result in a total cost of $266.3 million for the USNS POINT LOMA.
Base $2.7M+$6.3MRevised $9.0M
Decreases (sources)1 line / -$6.3M
ProgramProgram baseChangeRevised
DDG-51
Shipbuilding and Conversion, Navy 14/25 BA 02: Other warships
Funds are available due to funds being excess to program requirements. The USS DELBERT D BLACK (DDG 119) delivered in April 2020. The ship completed its post-shakedown availability in July 2021 and reached the obligation and work limiting date on August 31, 2021. Wt Cond ws (2H
Base $1.5B-$6.3MRevised $1.5B
Records on this page4Verified federal records
Largest value shown$1.5BAnnounced or obligated
Platform coverage$1.40TDoD & DHS obligations FY24-26
Expiring recompetes300$126.8B ending by Jun 2028
Timing

Budget books show money requested, enacted and spent by fiscal year before contracts show it. Enacted procurement money stays available to obligate for 3 years, RDT&E for 2 years and shipbuilding for 5, so a line funded this year turns into contract awards over the following 1 to 5 years. DoD contract actions then publish on USAspending about 90 days after signing (DFARS PGI 204.6), so the awards database trails these budget lines by months to years. Reprogramming actions move enacted money between accounts during the year, usually ahead of the awards it funds.

Trace Pentagon budget lines (R-1 / P-1) directly to prime contracts, incumbents & expiring awardsMatch every program element to the contracts that fund it, see who holds the work, and get alerted when it recompetes - 7-day free trial.
Trace PE-to-Contract Crosswalk in Terminal

Export CSV spreadsheets, query the API or get the daily contract email.

Pay as you go: $49 one-time for 1,000 API calls and browser CSV downloads (no account needed), or $0.02/call ($0.05 daily list). Subscriptions: Full Tape email $49/mo, Terminal $199/mo (10,000 calls/mo + CSV export), Team $599/mo (5 seats, 50,000 calls/mo).

Compare plans