Summary on the form
This reprogramming action transfers $18.300 million back to the Operation and Maintenance, Defense-Wide, 24/25, appropriation from amounts originally transferred to Other Procurement, Air Force, 24/26, and Research, Development, Test, and Evaluation, Defense-Wide, 24/25, as part of internal reprogramming action executed on September 6, 2024, FY 24-57 IR (Israel Security Replacement Transfer Fund Tranche 2). This transfer is pursuant to authority in title I of division A of Public Law 118-50, the Israel Security Supplemental Appropriation Act, 2024.
Accountsfrom and to
| Appropriation | Years | Change |
|---|
Operation and Maintenance, Defense-Wide receives | 24/25 | +$18.3M |
Other Procurement, Air Force gives | 24/26 | -$4.8M |
Research, Development, Test and Evaluation, Defense-Wide gives | 24/25 | -$13.5M |
Increases1 line / +$18.3M
| Program | Program base | Change | Revised |
|---|
Israel Replacement Transfer Fund Operation and Maintenance, Defense-Wide 24/25 BA 04: Administration and Servicewide Activities Funds provided as part of the September 6, 2024, internal reprogramming action FY 24-57 IR (Israel Security Replacement Transfer Fund Tranche 2) are transferred back to the Operation and Maintenance, Defense-Wide, 24/25, appropriation. This is a congressional special interest ite ... | Base $1.8B | +$18.3M | Revised $1.9B |
Decreases (sources)2 lines / -$18.3M
| Program | Program base | Change | Revised |
|---|
0603892C AEGIS BMD Research, Development, Test and Evaluation, Defense-Wide 24/25 BA 04: Advanced Component Development and Prototypes Funds are available for return because the amount transferred to Missile Defense Agency via FY 24-57 IR (Israel Security Replacement Transfer Fund Tranche 2) was in excess of the required amounts for development of advanced, high fidelity AN/SPY-1 Radar simulations to test system ... | Base $603.7M | -$13.5M | Revised $590.2M |
USCENTCOM Other Procurement, Air Force 24/26 BA 03: Electronics and Telecommunications Equip Funds are available for retum and excess to need due to an error which duplicated the USCENTCOM Automated Multi-mission Spectrum Monitoring requirement in the FY 24-57 Internal Reprogramming for Israel Security Replacement Transfer Fund Tranche 2. This is a congressional special ... | Base $11.9M | -$4.8M | Revised $7.1M |
Records on this page6Verified federal records
Largest value shown$1.9BAnnounced or obligated
Platform coverage$1.40TDoD & DHS obligations FY24-26
Expiring recompetes300$126.8B ending by Jun 2028
Timing
Budget books show money requested, enacted and spent by fiscal year before contracts show it. Enacted procurement money stays available to obligate for 3 years, RDT&E for 2 years and shipbuilding for 5, so a line funded this year turns into contract awards over the following 1 to 5 years. DoD contract actions then publish on USAspending about 90 days after signing (DFARS PGI 204.6), so the awards database trails these budget lines by months to years. Reprogramming actions move enacted money between accounts during the year, usually ahead of the awards it funds.
Trace Pentagon budget lines (R-1 / P-1) directly to prime contracts, incumbents & expiring awardsMatch every program element to the contracts that fund it, see who holds the work, and get alerted when it recompetes - 7-day free trial. |
Export CSV spreadsheets, query the API or get the daily contract email.
Pay as you go: $49 one-time for 1,000 API calls and browser CSV downloads (no account needed), or $0.02/call ($0.05 daily list). Subscriptions: Full Tape email $49/mo, Terminal $199/mo (10,000 calls/mo + CSV export), Team $599/mo (5 seats, 50,000 calls/mo).